cancel
Showing results for 
Search instead for 
Did you mean: 

sender cost is incomplete and Document balance cannot be distributed when settlement is reversed in CJ88

former_member613562
Participant
0 Kudos

Dear All

I am facing an issue while settling the project cost settlement to AUC in the capital project.

When i do the Test Run in CJ88, it shows a message in Green Color "Sender Cost is Incomplete", If i ignore the same and do the actual settlement then the cost is getting settled but on a contrary it cannot be reveresed and at that time it shows a error message as "Document balance cannot be distributed when settlement is reversed"

Currently we are working in ECC6 at EHP 6 level

Do let me know if we are missing any configuration

Thanks and Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hey Simon,

See this wiki page. It says to implement note 1671353.