HI All, can somebody tell me what is the use of the CoCD field in CK40N?

It does not block the selection of materials from other company codes in the costing run, so must have some other purpose.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jan 16, 2013 at 10:16 AM

    Hi Piet,

    It will restrict the cost estimate for materials from the relevant company code. Still have doubt, take the material which is not under in one Company Code and run the cost estimate and check.

    Regards

    Srinivas Salpala

    Add a comment
    10|10000 characters needed characters exceeded

    • Ho Piet,

      I have tested whatever you said by giving plant and without plant related other company code. But there is no difference in my case.

      First I have taken one company code and only material I have given the under parameters. Here, it dispalys "No material exists".

      Again, next time I have maintained the same company code, and in Parameters tab, I have choosed other company code's palnt and material. According to you, it should pick the material from the plant irrespective of company code.

      But, again It shown the same message "No material exists"

      Regards

      Srinivas Salpala

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.