Hi all,

I've created some routing groups (transaction CA01).

Now I would like to link some materials to the routings. Going in the routing header (CA02) there are 2 options (buttons):

- Material assignment

- Comp alloc

What's the diference between these 2 possibilities ?

Which one should I use ?

thank in advance for your help.

Fred

Accepted Solutions (1)

Accepted Solutions (1)

krishna_chandra5
Active Contributor
0 Kudos

Hi,

     Please go through the below explanations

Material assignments: Generally after creating a routing for one material or without material, you can assign the same routing to another material also. For this purpose the material assignment option will be used.

Component allocation: This is for the allocation of the components of header material present in the BOM to the corresponding operations.

Hope this clarifies. Revert back in case of further queries.

Regards,

Krishna Chandra

frederic_r
Participant
0 Kudos

Hi Krishna,,

thanks very much for your quick answer.

Regards

Fred