on 01-05-2017 5:58 PM
I understand how to do the 309 movement at IM level. How do we do this at the WM level so that we see the correct batch in the correct bin?
I would recommend a WM training as this question seems that the basic concepts are not known. reading help.sap.com documentation is also a good start.
WM is a sub to IM, the only thing you can do independently from IM is to transfer goods from storage bin A to storage bin B.
Anything else has usually its origin in a IM movement. You do your 309 in IM and get either a transfer request or a posting change notice depending on your customizing. And this has then to be converted into a TO which need to be confirmed when it is done.
So you either missed a step in your process or your WM consultant missed some customizing if you didn't get the TR or PCN.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Just complementing the answer above: The same way on IM level you have material documents formalizing the transfer, to have inventory moved in WM level you need a Transfer Order (LT03 Transaction). That will actually move the material inventory you see on LS26.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.