Skip to Content
0
Former Member
Jan 10, 2013 at 06:53 AM

BPC MDX Processing dimension after the EHP 6 Upgrade

19 Views

Hi Experts,

In my BPC box, I have one dimension with with MDX calculation. I could process the dimension successfully without the MDX formula but when I process the dimension with the MDX formula. I get the following error:

MDX statement error:"Node 0 with predecessor 0 not found in hierarchy

Below is the MDX formula, unable to process:

([VARIABLES].[GROSS_COST],[ACTIVITY].[STOPING],[PRODUCT].[ALL_PRODUCT_H1],[PRODUCT_TYPE].[ALL_PRODUCT_TYPE_H1])/([VARIABLES].[TOTAL_M2],[ACCOUNT].[NO_ACCOUNT],[ACTIVITY].[STOPING])

We are getting this error after the EHP 6 upgrade of BW

Your help in this regard will much appreciated.

Thanks,

Themba