Hi SCM Gurus,
While doing time series administration, I have performed /SAPAPO/TSCONS - Consistency Check of Time Series Network and found the following
"
Message no. /SAPAPO/TSM424
Check for the initialization periods of the key figures"
I have initialized the planning area by executing the program " /SAPAPO/TS_PAREA_INITIALIZE" with the following inputs
1) Planning Area
2) Planning Version
3) Update Master Data (Check Box)
3) Global Period From Date: 01/01/2008 to Date 12/31/2014
4) Key Figure Periods maintained
and PA has successfully initialized.
I have re-performed the /SAPAPO/TSCONS - Consistency Check of Time Series Network and still find the log "Key figure initialization horizon check" with repaired status as blank.
Your inputs are highly appreciated.
Thanks in advance.
Sai