Work Center Shift in CM25 scheduling

matteo_bongiorno
Participant
0 Kudos

Hi gurus,

i face a problem with workcenter capacity.

When i set shift in workcenter capacity, these intervals are not shown in CM25 scheduling, that continues to show standard workcenter capacity defined in capacity header. I'm not able to understand where this thing is set.

Any suggestions?

Thanks in advance.

Regards.

Matteo

Accepted Solutions (1)

Accepted Solutions (1)

matteo_bongiorno
Participant
0 Kudos

hi,

workcenter is active for finite scheduling. I enter in CM25 and i find the following situation, where available capacity is from 8 to 17 like defined in standard capacity.

Now i select the WC line, go to -> capacity -> change and i insert a new interval.

After i turn back to CM25 but the situation doesn't change, also if i go to Setting --Shift Calendar---Show (this only divide the available capacity in shift if you have defined more than one in a single day).

In another customer system, if i do the same path when i turn back to CM25 i see the shift in the GANTT.

The problem is that also if i define different capacity for a period, the system continue to show the standard capacity. I don't understand why. CM25 customizing is the same in both systems.

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

It is due to you are using the standard available capacity. You have to assign the shift sequence to your work center please configure the shift sequence in OP4A and the assign it your work center in CR02.

Please test the same and come back.

Regards,

R.Brahmankar

matteo_bongiorno
Participant
0 Kudos

YES. I GOT IT!!!!!!

I set the active version and i got it.

But i don't understand why in some systems, also in if not set active version, the result is the same. This is the reason why i could't solve the issue....

Thanks a lot however!

Bye.

M.

Answers (3)

Answers (3)

matteo_bongiorno
Participant
0 Kudos

Dear friends,

thanks for your answers.

i haven't solved my problem yet, also with your suggestion.

the problem is not CM25 configuration i think, because in two different customer systems, using the same sap standard CM25 profile, SAPSFCG001 (i controlled all the customizing and it is the SAME), the system behaviour in different.

In the first one, if i define shift, when i come back to CM25 i can see that the capacity in the GANTT changed according to the new shift, in the other system this doesn't happen.

@Rupesh, in the system where shift works the indicator is not set....

Thanks for your support.

M.

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Please check your work center active for Finite scheduling and active version and shift should maintain in your work center.

In CM25 with profile SAPSFCG001 enter your work center and plant,

then Select your work center and go to Setting --Shift Calendar---Show.

Regards,

R.Brahmankar

0 Kudos

matteo.bongiorno Were you able to fix this?

mynynachau
Community Advocate
Community Advocate
0 Kudos

Hi there,

You have a question and need help by the community? In case you don't find what you're looking for, it is more helpful for you, if you post your own question. Here is how to get started:

  1. Learn about asking and answering questions in SAP Community with this tutorial: https://developers.sap.com/tutorials/community-qa.html
  2. Ask your detailed question here: https://answers.sap.com/questions/ask.html
  3. Wait for a response.

That's it. Thank you!

Best regards

Your SAP Community moderator

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

In planning table via CM25 go to Settings>Shift Calendar>Show

In the time scale profile, Transaction OPG4 and OPG3 if the indicator 'Show shift calendar' is set to display the shift calendar in the first line when initially loading the graphical planning table.

Regards,

R.Brahmankar

Former Member
0 Kudos

Dear Matteo,

  • From CM21/CM25 - Click on the 'Strategy' button --> Check is the 'Finite Scheduling' is ticked for the selected Strategy profile.
  • Also, please check if the 'relevant to finite scheduling' indicator is set to the Workcenter - capacity tab.

Regards,

Senthil