Factory Calendar ID is not defined.

Hi all,

When I am creating project in CJ20N in my production client, an information pop-up box is getting generated as Factory Calendar ID is not defined. But the factory calendar from project profile is replicating in CJ20N. Even though i proceed and try to create Network Activity its asking me to enter start date & End date. But there is no any calendar to select nor its allowing to enter the dates manually,its showing "The Factory Calendar ZI does not exist(contact systems Administrator).

I checked with my PP consultant, he told that its working fine for his process in production. For my development client & in quality there was no any issue regarding factory calendar,its working fine.

Is anything went wrong from PS side? Kindly show the solution.

Kindly check the attachment.

Thank you

Seshagiri

fact cald.png (259.6 kB)
Add comment
10|10000 characters needed characters exceeded

5 Answers

  • Best Answer
    Posted on Jan 03, 2013 at 11:04 AM

    Hi

    Thank you Ankur for your response.i checked OX10, the factory calendar ZI is assigned to the plant.

    Gokul-Kindly check the below error message numbers:

    After creation of Project definition - Message number CO503.

    When creating Network

    Message No.CO034.

    Diagnosis

    An internal error has occurred.

    System Response

    Processing stopped.

    Procedure

    Contact your system administrator.

    Regards,

    Seshagiri

    Add comment
    10|10000 characters needed characters exceeded

    • Thank you Gokul for your support.

      Its working fine now. Informed to my Abaper. He just Activated the Factory calender which was present in SCAL . Earlier it was not activated by PP person.

      Thanks to all. Hence closing this Thread.

      Regards,

      Seshagiri

  • Posted on Jan 03, 2013 at 09:59 AM

    Hi

    Do one thing, Check in OX10 whether factory calender is assigned to the respective plant or nor.

    Please check & revert.

    Rgd

    Ankur

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 02, 2013 at 12:36 PM

    Hello,

    You should check in Transaction SCAL if factory calendar Z1 has been created and if it has a valid period ( you cannot plan a project out of the calendar validity period)

    Regards,

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Seshagiri Konathala

      Hi Seshagiri,

      Not sure if I've understood your issue :

      If you have a project/WBS and open the matchcode for calendars --> You see the factory calendars.

      If you are creating a network and open the matchcode for calendar --> You don't see nothing.

      It is very strange, the only I can think it is the system is checking you the planning calendar ( transaction MD25) instead of the factory calendar.

      Could you check this option?...

      Regards

  • author's profile photo Former Member
    Former Member
    Posted on Jan 03, 2013 at 08:26 AM

    have you check opsa project profile planning board/date tab where you have to fix factory calender as Z1 you said.

    Regards,

    Aryan

    Add comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 03, 2013 at 09:21 AM

    Hi Sara , Gokual & Aryan,

    Thanks a lot for your response...

    Sara- I checked MD26,but there is no any planning calendar...it shows No values for selection.

    Aryan- The ZI calendar is replicating because of assigning the said ZI calendar in Project profile.

    Gokul - I also checked with FI/MM persons,they didnt change any config settings regarding said factory calendar.

    I am not getting why the system is showing contact your system administrator? ( as per screen shot that i had provided)

    Regards,

    Seshagiri