on 12-27-2012 9:29 AM
Hello All,
My requirement is to transfer Quality Inspection stock between two storage locations of the same plant using a two step stock transfer (movement type - 313 & 315). The QM module has not been implemented.
The issue is that when I do a 313 to move stock to in transit and using stock type 'Quality Inspection' for a material for which QI stock exists in MMBE. On posting, it takes stock from unrestricted stock(decreases) instead of QI stock whereas I would want it to pick the QI stock.
Please explain if there is any standard route to achieve the same based on some movement type config changes (create a custom one and then make changes to achieve this). We are not looking for any user exit/enhancement here..
Please suggest.
Thanks,
L. Philip
Hi,
stock transfer between Sloc to Sloc will effect on unrestricted stock only.
you can't transfer qulaity stock untill you QM release.
if you want transfer Sloc to Sloc with QM, then change material master and apply 08 inspection type.
Ajay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Stock transfer between storage locations in 2 step procedure can be done only for Unrestricted use stock type. And that is why your unrestricted use stock is getting reduced during 313. This is SAP std.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.