MRP for Lead time scheduling

241 Views

I am running MRP through MD02 by selecting the Lead time scheduling, but it is not calculating the routing values of Setup time and machine time and labor time. It is simply giving the date same as Basic date scheduling.

We have following settings :

1. Work center Capacity tab has been defined with proper data lilke Standard value parameter, formulas, Scheduling formulas in Scheduling tab.

2. Work center Capacity Tab also assigned with start time, end time, no of individual, efficiency and fine scheduling activated.

3. MRP control parameters also maintained as shown below screen shot:

Please help in resolving this issue.