on 12-20-2012 5:09 PM
Hello All,
We have a situation. I'm not able to create a production version with BOM and Routing assigned. We should create a PV with suitable BOM and Routing along with REM activated. While creating it we are getting the follwoing error:
BOM and routing cannot be changed. See long text
Message no. KOSA401
Diagnosis
You are attempting to change the entries for the BOM or for detailed or rate-based planning in production version XXX of material YYY in plant ZZZ. Because the controlling level BOM/Routing is assigned to material YYY in plant ZZZ, and because production version XXX is used in repetitive manufacturing, changing the entries for the BOM or for detailed or rate-based planning would result in the use of the wrong product cost collector in repetitive manufacturing for production version XXX. For this reason, it is not permissible to change entries for the BOM or for detailed or rate-based planning in production version XXX.
Can anyone let me why this issue comes and the possible solution to resolve this issue? I'm not able to delete the existing production version (Without BOm and Routing) also as it is displaying the same error message.
Your valuable inputs are much needed.
Thanks,
NW
Hi NW,
First check any procurement proposal exist against that version, If yes close it properly .
After closing procurement proposal you can able to set deletion flag to this version or create new version with new validity & assign BOM & Routing to version.
Please check KKF6N .
Note:-Procurement proposal means it may be production order or if externally procure check PR,PO.
Also check cost settlement rule if assign to production order settle it properly.
Regards,
Shyam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You have selected the BOM/Routing while creating Product cost collector for material through KKF6N9 which determines the controlling level for material.you need to change that in T code CKMLMV_CA.
Check and revert
Regards
Anupam Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you are trying to change any production version first check whether any procurement elements are existing in the system. Follow the steps mentioned below
Check and revert back.
Note: Why you have posted four discussions with the same question. Please avoid this in future as this creates confusion.
Regards,
Krishna Chandra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.