How to exclude Open Production Order in Demand Management.

145 Views

Dear Gurus.

I using Planning Strategy 11 for material "X",this material having open Production order for quantity 100 which is not confirmed but released.Now I am entering PIR for Material "X" of 50 Quantity,When I am running MRP, system not generating any Planned Order for this requirement and consume the open order quantity.

I want to exclude this Open order quantity and to create Planned order for material X having quantity 50.

Please suggest how can we map this Process in SAP.

Thanks.

Nitin