MRP Consumption based planning

sb_er
Active Participant
0 Kudos

Need to raise the P.R Through consumption based planning run.

Issue is i need to run MRP for list of materials. how to do? any seperate T code is there?

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

I think you can use product group option to run the MRP for mutilple materials in MD02, refer below thread for more details.

http://scn.sap.com/thread/1585669

Regards

Vijay

kirankumar_as
Explorer
0 Kudos

Hi,

 

To execute total planning materials, go to the the Transcation MD01 select (NEUPL,NETCH & NETPL according to ur req)

Individual Conversion of plnd order into PR from MRP go for MD14 trans

Collective Conversion of plnd order into PR from MRP go for MD15 trans

Select Plant & MRP controller u will get list of display

JL23
Active Contributor
0 Kudos

you can run MRP by single material or for all your materials in a plant or MRP area.

but there is no option to run it for for a list of materials.