on 12-17-2012 10:36 AM
Hello Gurus,
I am working on an enhancement project , where SAP is already implemented , and using REM (repetetive manufacturing)
we want implement product costing. Could you please guide me step by step procedure to implement this from PP perspective
.The configuration that is required to be done.
Thanks in advance
Regards
Aadi
Dear PP sap2012,
I'm not sure how you have implemented REM without product costing.
1. In a REM environment a Product cost collector for each material's production version is
maintained.
2.Only if a Product Cost collector exists for the combination of material,plant and production version,
the production confirmations can be carried out using MFBF.
3.Necessary settings should be first maintained in REM Profile under Control Data tab for posting
activities and backflush using preliminary cost estimate or else based on the standard cost estimate
of the material.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.