Dear Friends
even Confirming Maintenance order by IW41 also Actual End date not capturing in that concerned maintenance order where as Actual start is capturing
Why this happening please light up on this issue.
Regards,
Kumar
Greetings Kumar,
the Actual End date will only get updated if you post a confirmation with the Final indicator.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have you made final confirmation for that operation??
How many operations you have in that order?? If you have more than one operation for the order, all operations should have CNF - Confirmed status.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You ask your question in EAM forum ... http://scn.sap.com/community/eam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.