Skip to Content
avatar image
Former Member

Actual End date

Dear Friends

even Confirming Maintenance order by IW41 also Actual End date not capturing in that concerned maintenance order where as Actual start is capturing

Why this happening please light up on this issue.

Regards,

Kumar

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Dec 17, 2012 at 09:23 AM

    You ask your question in EAM forum ... http://scn.sap.com/community/eam

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 17, 2012 at 09:49 AM

    Have you made final confirmation for that operation??

    How many operations you have in that order?? If you have more than one operation for the order, all operations should have CNF - Confirmed status.

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 17, 2012 at 09:50 AM

    Greetings Kumar,

    the Actual End date will only get updated if you post a confirmation with the Final indicator.    