Dear All,

I am giving PIR of FG and run MRP for it by MD02 then check the results, it has been found that two SF material's not planned also they are not seen in planning result.

I have checked in Material Master for both SF materials, it found ok. Then I have checked BOM of FG in CS03 then I have seen that for both the SF materials line item in column "Change No.", "0001A" mentioned.

Hence I have run MRP for FG material by keeping planning mode '2' but even though BOM not exploded. Also checked stock of both SF materials in MMBE, no stock found.

Kindly suggest Why BOM not exploded?