I have modified a smart form and also modified a standard text used in the form. I have kept the smart form and the standard text under a same
TR (D01K907841) and transported the TR from Development server to Quality server. Now again I have modified the smart form and save it in a new TR(D01K907843) and again transported the new TR from development to quality server. My question is which TR I have to transport from quality to production server so that all the changes effect in the production server?
Regards
Dipanjan Majumder
12-13-2012 9:15 AM
If the standard text is not in the second transport request, you should be required to transport both requests (in correct sequence of course)
Regards,
Raymond
12-13-2012 9:15 AM
If the standard text is not in the second transport request, you should be required to transport both requests (in correct sequence of course)
Regards,
Raymond