Statistics-Relevant Delivery Date in PO

jaheer_hussain
Active Contributor
0 Kudos

Hi,

In the PO item tab(Delivery schedule),system insert delivery date  as statistical delivery date when I donot enter statistical delivery date.  I want to stop it. Is it possible?

With Regards,

Jaheer

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member

The statistical delivery date is basically used for vendor evaluation. It is changed along synchronous with the delivery date, if you have not yet outputted the order. After the output, the statistical delivery date will not change automatically with a delivery date change.

The reason is, the delivery  is used for your planning, while the statistical del date  is used for vendor evaluation. If the vendor says he cannot meet the expected delivery date, then you  change the delivery date to the new date to make your planning information accurate. But the statistical del date will stay untouched, you evaluate your vendor against this Stat del date and he gets a bad rating because he did not meet your delivery date.

Why do you want to stop it?This does not have any implications to the business I presume...

jaheer_hussain
Active Contributor
0 Kudos

Hi,

Thank you for reply.

Initially vendor gives one delivery(20.12.2012) and later vendor sends commuication  saying he can delivery on (27.12.2012).I want to enter this latest delivery date(27.12.2012). Where to enter this in the system? This is my requirement.

With Regards,

Jaheer

Former Member
0 Kudos

Hi,

   you change the delivery date no need to maintain statastical delivery date (i think)

Former Member
0 Kudos

Hi,

Delivery date is date suggested by the system based on your material master or info record planned delivery time. You cannot pre-pone that, only postpone it.

For that purpose statistical delivery date is used (of course apart from Vendor Evaluation).

Alternatively if your version management or release is linked to change in delivery date then you use statistical delivery date. Also if you know delivery will be delayed to due un-avoidable circumstances (beyond human control) that time you can change statistical delivery date.

Regards