on 12-12-2012 5:43 AM
hi,
i a bit confused of status CNF which is confirm.
1 under what kind of several situation, the order status is turned to CNF?
2 CNF and (DEL or TECO) are different. what actually is the difference between them?
thanks
Hi,
After confirmation of the production order, system will shows the CNF status.
The status of production order confirmation will be REL PCNF DLV PRC GMPS MACM SETC.
Hope this helps you.
Regards,
Puri.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
If you create a order for 100 quantity and you done full 100 confirmation the order status will show CNF other wise if you done 50 Confirmation order status will show PCNF.
If you want to make DLV status in goods receipt tab active delivery indicator
If you want to make TECO status in menu process order--> Functions--> Restrict processing--> Complete technically.
Regards,
Ravi.
Confirmation means activity confirmation, to produce any materials you requires raw material cost, activity cost and over head cost.
So at the time of confirmation the activities cost will flow on to the order and cost center will become zero
The co entry at the time of confirmation is ORDER DR AND COST CENTER CR.
Regards,
Ravi.
Hi,
CNF = confirmation of goods and activities
DEL = after fnal GR it will represent
TECO = technically complete (we can do it manually or automatically)
Regards
Srinivas Salpala
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.