The PO’s successfully created but PI sheet not created for the orders.

How to create PI Sheet for finish and semi-finished products?

Can anyone assist me.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member214725
Active Participant
0 Kudos

Hi,

Check if you have released the control recipes in the order and then check in CO53 for the released instructions.

Your question too is very generic, provide more details....

Former Member
0 Kudos

How to create a PI Sheet

am new to PP PI

Former Member
0 Kudos
 
Dear,

In additon of above points, You can check below configuration steps.

·         SPRO-->PPPI --> PROCESS MANAGEMENT --> CONTROL RECIPE/PI SHEET --> DEFINE & SETUP CONTROL RECIPE DESTINATIONS

·         SPRO-->PPPI --> PROCESS MANAGEMENT --> CONTROL RECIPE/PI SHEET --> SELECTION VARIANTS FOR PI SHEET --> DEFINE SELECTION VARIANTS FOR PI SHEET

·         SPRO-->PPPI --> PROCESS MANAGEMENT --> CONTROL RECIPE/PI SHEET --> SELECTION VARIANTS FOR PI SHEET --> ASSIGN SELECTION VARIANTS FOR PI SHEET

·         SPRO-->PPPI --> PROCESS MANAGEMENT > DEFINE PI CATEGORIES FOR PI SHEET.

You should follow these above configuration steps in PI sheet.

After the above configuration Maintain the control recipe destination in recipe then assign the process instructions to the operations.

Then follow the below steps.

COR2 Generate After creating the process order release

CO53 Control Recipe Monitor Send the control Recipe

CO58 PI Sheet Maintain Input the values in the control recipe (PI sheet)

Check & Revert.

TnX

Former Member
0 Kudos

Very usefl information.

Can u send me Screenshots of the processes. It would be great help.

I need to do it on friday at my client place.

I can give you few points for the help as well