Skip to Content
avatar image
Former Member

Shelf Life Expire Date

Is there any provision for  Trigger Inspection lot against  shelf life Expire date now we are trigger inspection lot based on  inspection intervals what we maintained in Material Master. SLED we are maintained  against Batch at the time of  Usage Decision.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Dec 12, 2012 at 11:30 PM

    No.  there is not.

    But there is a user exit you can use to keep the two values in sync using whatever logic your company wants to use.

    The exit is:

      QEVA0003 Calculate "Next inspection date" for batch                 

    FF

    Add comment
    10|10000 characters needed characters exceeded