Hi experts,

I have a requirement for the production order qty , i need the cost of at Multi level Bom for Produced qty for a production order. IN Ck13n We will get Assembly wise drill down... the same way i need the actual cost for production qty with drill down availability.

is there any Z report... help me

Thanks

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on Dec 10, 2012 at 07:41 AM

    Hi,

    Please check:

    CO03->Goto-> costs-> Anlysis

    or use the std. report KKBC_ORD.

    Also check the below link:

    http://scn.sap.com/message/10154013

    Regards,

    Alok Tiwari

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 10, 2012 at 07:43 AM

    Hi,

    Pls check below report for multilevel BOM CK86_99

    check & revert.

    TnX

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 10, 2012 at 11:38 AM

    Hi,

    In Ck11N you will be able to get the current actual price of the material.


    1.JPG (47.9 kB)
    1.JPG (68.0 kB)
    2.jpg (83.9 kB)
    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Ranjith,

      For production qty, After the co month end activities we will come to know that actual cost of production order qty.. At this level i need a drill down option at assembly level. if i look at co03 or kkbc_ord any other std report , just cost will roll up and add to next level. but we cant get drill at assembly level.. is there any z report we can prepare that can have the option of drill down at each level

      thanks

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.