Dear All,

While creating Sale Order System shows the message "No Availability Check Can Be Carried Out for the Material xxxxxx", whereas I have sufficient stock of that material.

Thanks & Regards,

Paramjeet Singh

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Dec 10, 2012 at 05:18 AM

    dear,

    please run MM02 for your material / plant and go to MRP3 view - fix the Availability check

    regards,

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 10, 2012 at 05:21 AM

    Hi Paramjit,

    You may take reference of below mention link

    https://scn.sap.com/thread/1339353

    Hope this will help you

    Regards

    AJC

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.