on 01-05-2017 9:24 AM
Hi All,
During Production subcontracting,
In Production order i have 7 operations to be performed on Product A.
As follows,
0010 PP01
0020 PP01
0030 PP02
0040 PP01
0050 PP02
0060 PP01
0070 PP03
As per my current settings, system is generating PR for operations 0030 and 0050 as soon as i save production order. However i want to generate PR, when operation 0020 is confirmed. Not at while saving production order.
BR,
Hello
On the order type dependent parameters customizing you can define that a requisition will be only generated when releasing.
Therefore, the solution to this issue is to release the operations independently, that means, relasing operations 0030 and 0050 only when operation 0020 is confirmed. You can define a trigger point to automatically release those operations upon the confirmation of the previous operation.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Caetano,
How to control the document type which is being picked for the PR getting generated from the Production Order?
Thanks
Ramakanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Caetano,
Thanks for reply, It solved my problem.
can i release the first operation automatically using trigger point. ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.