  Could anybody tell me the scenario on Auto UD by using of DMR(Dynamic modification rule) at skip lot level.

i have tried it but UD not happening automatically (i have maintain UD delay time in plant level settings) also.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Dec 06, 2012 at 05:05 AM

    1.) Maintain Waiting time (hrs) & mins for automatic UD in Maintain setting at plant level (Inspection lot completion tab) in SPRO -> QM -> Basic setting ->Maintain setting at plant level .

    2 ) Maintain DMR to all your MIC's or @ lot level ,which will skip the IL.

    3.) Maintain automatic UD for the inspection type in the material master.

        Maintain SKIP as well if you are using DMR.

    4)  Go to QA16 > Create variant > Specify inspection type, usage decision appropriately while creating variant. >Click on skip >  Schedule the job periodically( QA17).