To have QM implemented, should QM Plant parameters maintenance mandatory?

HI Friends,

I am using Automatic usage decision functionality and waiting time is maintained in QM Plant parameters to making use of in case User wants to intervene to reject the Lot.

My client is having ove 1000 plants already into SAP but QM is implementing now. So in this case to reduce certain customisation activities, is there any possibility to not maintain QM plant paramters IMG activity.

Is it possible without maintaining QM Plant paramters IMG to implement QM.

Thanks in advance

Nag.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Dec 05, 2012 at 12:14 PM

    Hey Nag Krish

    To implement the QM in differnet plant you have to do the plant level setting for each plant. When plant is created by MM guy, automatic entry of that plant is created in QM Customizing with defalut entries as provided by SAP.

    So you donot need to create the plant specifically for QM.

    Manish

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Nag Krish

      NO  its not possible because system reads the AutoUd time from plant settngs. Your problem is that you have thousands of plant to maintain AutoUd time. So you can make LSMW or BDC for maintianing that DATA.

      Manish