Hi,
CTM does not take into account production duration in PPM/PDS when calculating order start date in planned order. For example ;
- I have daily bucket in Planning book
- Demand is 96kg for 14.12.2012
- Poduction duration 1 hour for 1 Kg In PDS
- If we run ctm, system will create a planned order with Order start date : 13.12.2012 Order finish date :14.12.2012
** System just checks the fix activity duration which is 1 day in PDS (in mode tab)
But I need a planned order which must start 10.12.2012 because demand is 96kg and 1kg can be produced in 1 hour so I need 4 days for this production
The order start date must be 10.12.2012 and Order finish date must be 14.12.2012.
Is it possible to manage this process in SNP ?
Thanks
Halil