Clear individual sub items commitments for a service line item in Purchase orders.

Former Member
0 Kudos

Hi all,

I have a requirement to clear the commitments from sub items level inside a service PO line item.

If I put the "Delivery completed" indicator, the commitment of the line item is cleared as a whole.

Please explain how can the commitments of sub items inside a Service line item be cleared in a PO.

Thanks,

Vinod.

Accepted Solutions (0)

Answers (1)

Answers (1)

narasimhulu_konnipati
Active Contributor
0 Kudos

If the commitments are posted, then they will be disappeared. Let us say, you have 100 k commitments in PO, and posted 50k only through MIGO and MIRO, then you see only 50k in commitments. So, check why there are commitments and try to post them. If not required, cancel them.

Thanks

Former Member
0 Kudos

Hi Narasimhulu Konnipati,

In my scenario, the POs are created from PRs which are automatically generated through Project Systems module.

We require to clear the commitments of unused/ partially used items inside service line items, such that budget allocated for that sub items can be reused.

For example:

I have a PO with service line item 10.

10ND
Service 00021EAD19.12.2012300.00INR

Inside this service line item i have the following 3 sub items:

10
testing-110M310.00100.00INR
20
testing-210M310.00100.00INR
30
testing-310M310.00100.00INR

suppose only 8 M3 of sub item 10 is used, the value of remaining 2 M3 has to be cleared and returned to budget.

Putting delivery complete indicator is possible only at the main line item level but not in the sub item level.

Please let me know if there is any alternate method to clear the commitments at sub item level.

Thanks,

Vinod.

Former Member
0 Kudos

Hi Vinod,

Your enquiry is described in SAP note 772206. I believed you can set up the scenario according to SAP note  634298 (point 2).

Regards, Gordon

Former Member
0 Kudos

Hi Gordon,

My requirement is to clear the commitments at service specification level. Right now I can clear the commitments only at line item level by clicking the "Delivery completed" indicator. The problem is that if I clear commitments at line item level  the specifications which are still under process under the line item will get affected.

Thanks,

Vinod.