on 12-03-2012 6:10 AM
Hello Experts,
Good day!
I need help on how to edit material group in PO which is grayed-out.
I have checked and there are no subsequent documents. I have also checked the screen layout at document level and the material group field is already optional. With this, I should be able to edit it already, right?
Could you assist me on what else to check to be able to edit the material group in PO item level which is already grayed-out?
Thanks and regards,
Kaye
Sorry for my late answer. Mass maintenance of single or multiple purchase orders with transaction MEMASSPO works for me in the most cases. If it doesn't work for you, you'll at least get a reason.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Why you want to change material group in purchasing document?
Are you creating material purchase order or service purchase order!
When you create any purchasing documents such as PR,RFQ,contract , scheduling agreement and purchase order for for material, then material group should flow from material master and during creation ,you should not allow to change material group for that material master.
If you are creating service purchase order,then material group/service group flow from setting in t.code:ML91 where it maintaioned in field of Default Material Group at Item Level.
NOTE:
In future or now, report needed based on material group and if you are able to change material group in purchasing document that will reflect the true statistics of report!
Regards,
Biju K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Go to OLME Tcode - Purchase Order - Define Screen Layout at Document Level - Select AKTA - click on Basic Data, Item - Make it as Optional/Mandatory as per requirement.
Do this for AKTE, AKTH, AKTV, ME21 and NBF.
Check in PO.
Thanks,
Shiva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Even if you try the above method, it is not going to work, simple thing is Material group is picked from Material master and not possible to change the material group in Purchase order. If GR is not done, then delete the line item and go to MM02, change material group and proceed for PO.
Thanks
Rajani
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.