Dear All,

As per my client requirement the shift details are as follows

A: Morning shift(6 AM to 2 PM).

B: Day Shift( 2PM to 10 PM)

C: Night Shift( 10 PM to 6 AM)

G: General Shift ( 9.30 AM to 5:30 PM)

D: Day Shift( 8AM to 4 PM)

N: Night Shift_Early ( 8 PM to 4 AM)

Shift pattern on weekly basis is

1st week:

CCCCCCR.

2nd week:

BBBBBBR.

3rd Week:

AAAAAAR.

4th Week:

CCCCCCR.

1st week:

DDDDDDR.

2nd week:

NNNNNNR.

3rd Week:

DDDDDDR.

4th Week:

NNNNNNR.

For General shift the pattern is GGGGGGOFF.

As per the requirement, the DWS details are as follows

1. ADWS(Morning shift)

2. BDWS(Day Shift)

3. CDWS(Night Shift)

4. DDWS(Day shift)

5. NDWS(Night Early shift)

6. GDWS(General Shift)

7. OFFD(Off day)

The PWS details are as follows

GPWS( For General shift Monday to saturday and sunday off): 01. GDWS, GDWS, GDWS, GDWS, GDWS, GDWS, OFFD

SPWS(FOR A, B AND C Shifts): 01. CDWS, CDWS, CDWS, CDWS, CDWS, CDWS, OFFD

02. BDWS, BDWS, BDWS, BDWS, BDWS, BDWS, OFFD

03. ADWS, ADWS, ADWS, ADWS, ADWS, ADWS, OFFD

LPWS( 8 AM to 4 PM and 8 PM to 4 AM) : 01. DDWS, DDWS, DDWS, DDWS, DDWS, DDWS, OFFD

02. NDWS, NDWS, NDWS, NDWS, NDWS, NDWS, OFFD

As per the above PWS the WSR is generated.

Plz guide me for Shift planning configuration...