Dear All,
As per my client requirement the shift details are as follows
A: Morning shift(6 AM to 2 PM).
B: Day Shift( 2PM to 10 PM)
C: Night Shift( 10 PM to 6 AM)
G: General Shift ( 9.30 AM to 5:30 PM)
D: Day Shift( 8AM to 4 PM)
N: Night Shift_Early ( 8 PM to 4 AM)
Shift pattern on weekly basis is
1st week:
CCCCCCR.
2nd week:
BBBBBBR.
3rd Week:
AAAAAAR.
4th Week:
CCCCCCR.
1st week:
DDDDDDR.
2nd week:
NNNNNNR.
3rd Week:
DDDDDDR.
4th Week:
NNNNNNR.
For General shift the pattern is GGGGGGOFF.
As per the requirement, the DWS details are as follows
1. ADWS(Morning shift)
2. BDWS(Day Shift)
3. CDWS(Night Shift)
4. DDWS(Day shift)
5. NDWS(Night Early shift)
6. GDWS(General Shift)
7. OFFD(Off day)
The PWS details are as follows
GPWS( For General shift Monday to saturday and sunday off): 01. GDWS, GDWS, GDWS, GDWS, GDWS, GDWS, OFFD
SPWS(FOR A, B AND C Shifts): 01. CDWS, CDWS, CDWS, CDWS, CDWS, CDWS, OFFD
02. BDWS, BDWS, BDWS, BDWS, BDWS, BDWS, OFFD
03. ADWS, ADWS, ADWS, ADWS, ADWS, ADWS, OFFD
LPWS( 8 AM to 4 PM and 8 PM to 4 AM) : 01. DDWS, DDWS, DDWS, DDWS, DDWS, DDWS, OFFD
02. NDWS, NDWS, NDWS, NDWS, NDWS, NDWS, OFFD
As per the above PWS the WSR is generated.
Plz guide me for Shift planning configuration...
Thanks,
Santosh