ESDMA generation taking 4-5 days to complete

Former Member
0 Kudos

Hi ,

ESDMA queue generation on SAP NWM is taking around 4-5  days to complete. It is too long time for us to estimates cutover time before go live.SAP  have proposed us to go to SP02 to increase the perfomance of SAP NWM but some how we cannot apply that patch right now,

So can we do following steps before production go live:

i)Run the ESDMA queues without connecting it to CRM, it will complete some 95 % of queue.

ii)rest 5 % which require CRM connectivity will be completed during cutover activity.

In this way during cutover to PRD  we will be only doing running 5 % of queues and hence save time.

iii) I know that during ESDMA geneartion data objects are activated , but do we need CRM system connected always to generate these data objects.

What exactly can be reason of ESDMA generation taking such a long time.

Can we do step i and ii and break ESDMA generation in bit sized piece. Will it have any impact on sucessful ESDMA generation.

Regards

Nidhideep Bhandari

Accepted Solutions (0)

Answers (2)

Answers (2)

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Have you applied all notes listed in here?

http://scn.sap.com/docs/DOC-30002

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

I think something wrong in your system setup.

What is your system environment?

ESDMA name:

Memory on server:

CPU on server:

SAP_BASIS version and SP:

CRMSPGWY version and SP:

Kernel patch version:

Former Member
0 Kudos

Hi Masayuki,

Please find details below:

What is your system environment? -Windows

ESDMA name:MAS_CRMSALES , 2.0 of  SAP

Memory on server:8 GB

CPU on server:4

SAP_BASIS version and SP: 710 .0015

CRMSPGWY version and SP:110,008

Kernel patch version:720