on 11-26-2012 5:57 AM
Hi ,
ESDMA queue generation on SAP NWM is taking around 4-5 days to complete. It is too long time for us to estimates cutover time before go live.SAP have proposed us to go to SP02 to increase the perfomance of SAP NWM but some how we cannot apply that patch right now,
So can we do following steps before production go live:
i)Run the ESDMA queues without connecting it to CRM, it will complete some 95 % of queue.
ii)rest 5 % which require CRM connectivity will be completed during cutover activity.
In this way during cutover to PRD we will be only doing running 5 % of queues and hence save time.
iii) I know that during ESDMA geneartion data objects are activated , but do we need CRM system connected always to generate these data objects.
What exactly can be reason of ESDMA generation taking such a long time.
Can we do step i and ii and break ESDMA generation in bit sized piece. Will it have any impact on sucessful ESDMA generation.
Regards
Nidhideep Bhandari
Have you applied all notes listed in here?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think something wrong in your system setup.
What is your system environment?
ESDMA name:
Memory on server:
CPU on server:
SAP_BASIS version and SP:
CRMSPGWY version and SP:
Kernel patch version:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
84 | |
24 | |
11 | |
9 | |
7 | |
6 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.