Dear Experts,

In our project scenario only WBS elements are present, no activities.

We have to perform Resource Planning. and CATS is out of scope.

My question ....1. is there a way we can assign resource to WBS elements ?, 2. can I post resource actual hours spent to WBS elements withouts CATS. ?

I know we can assign Project Team for a perticular WBS element. But I am not sure that the same can be used to book time. Also I cant find any report which shows this is the project team assigned for this project / WBS element.

Thanks in advance for the help.