MRP proposal & pegged requirement

45 Views

Hi Experts,

Need your advise:

Plant 1200:

FG#A, Procurement F, Special Procurement 30 Subcontract, GR processing-2days.

MRP view setting: Lot size EX

With PIR:

W50.2012, 5k

W06.2013, 5k

FG#A has BOM SFG#1 only.

SFG#1, Procurement F, Special Procurement 40 Stock Transfer (from producing plant 1000).

MRP view setting: Lot size EX, Dependant Req 01

FG#A, 1 pc = SFG#1, 1pc

MRP run result in plant 1200:

FG#A:

11.12.2012, PR 5k

11.12.2012, IndReq 5k

04.02.2013, PR 5k

04.02.2013, IndReq 5k

SFG#1:

07.12.2012, PR 10k

07.12.2012, SubReq FG#A 10k

Pegged PR detail for SFG#1:

11.12.2012, IndReq FG#A 5k

04.02.2013, IndReq FG#A 5k

Pegged PR detail for SubReq FG#A 10k:

11.12.2012, IndReq FG#A 5k

04.02.2013, IndReq FG#A 5k

Question: Why system pegged together requirement of Feb,2013? How to make it individual pegged/PR proposal?