Dear Experts,
In MCI8 I can get all the actual and planned cost ( Labor, Spare Parts , services ....etc) inquired by order types, equipment or Functional Location and this can be done by assignment of the cost elements to the value categories, however my client request is to know all the inquired costs by WORK CENTER, i know that this can be done using IW38 but it will show me the total actual costs only.
Is there any idea to do something like MCI8 for but for Workcenets?
Much thanks in advance,
Serry