Dear All,
My Scenario is,
I am using strategy 40. I have created sales order for FG. In sales order, I have put Req. delev. date as 21.12.2012.
Now I have run MRP on 21.11.2012 by MD02.
Result is,
When I have check result of MRP then found that one of my Raw material's PR release date is 29.11.2012(In ME5A).
My Question is,
Why system takes 29.11.2012 as a release date? Kindly know why it happens and what are the settings so that it will be released on 21.11.12.?
Note : I want this raw material as early as possible and for that system should release Pur. Req. on 21.11.12. For this material Planned deliv. time is 30 days because of that it will get on 29.12.2012 which is very late and crossed the FG deliv. date.
Waiting for reply from all you GURUS.
Thanks,
Naresh