How can I use new logical component for ChaRM in existing project

How can I use new logical component for ChaRM in existing project.    

Hi,

we are using Soulution Manager 7.0 sp28,

we have activated the change request management for ECC system. task list was created successfully.

now we have another requirement that we what to use the CRM system for the same project, we have assigned new logical component when i tried refreshing task list but we can't see the CRM system.

any expert can How can I use new logical component for ChaRM in existing project.

Thanks in advance!!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Nov 22, 2012 at 10:16 AM

    Hi,

    please check out the answer for the question no 6, here

    Change Request Management scenario: Usual questions and known errors

    Thanks,

    Jansi

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 22, 2012 at 10:21 AM

    Hi

    to add new logical comp close the current maintenance cycle and then add new system logical component and finally create new maintenance cycle.

    or check below blog

    Q6. Changes in the logical components of a project where Charm is already activated

    http://scn.sap.com/people/dolores.correa/blog/2009/07/22/change-request-management-scenario-usual-questions-and-known-errors

    don't worry about open changes these will be linked automatically to new maintenance cycle

    This will resolve ur issue.

    Regards

    Prakhar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 23, 2012 at 04:10 PM

    Although you should close and re-activate the maintenance as mentioned previous, you may be able to add the system if the project has been refreshed, but you will need to add them to the task list manually. 

    After added new logical component, refresh the project, go into the task list for the Project (SCMA) and click button "Change Task List", then "Add System" (folder button).  From here you should be able to manually add the new systems and any tasks.