Hi,
I have a scenario, where initially we have the task list with operations 10 ,20,30.......160 ... This is associated with the maintenance plan.
These operations were copied in orders which are created from IP10..
After that, we have increased operations from 10,20 .....200.....
Newly added operations were not copied in to orders which created after the task list modification..
I have removed the task list in maintenance plan and re assigned..But still it is not working...
Please suggest.
Regards
Chandru