Pricing Reference Material Change

Hi Gurus -

We have some materials (Finished Goods) which were earlier assigned as Pricing Reference Material itself. Now we want to change to Semi Finished but its not allowing me to do so. Any idea what the issue can be ?

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 20, 2012 at 04:19 PM

    Hi Ameet ,

    If there is any open documents assigned to the material, then you cannot change it. Make sure no open documents assigned to it.

    Refer the below link.

    http://sapmm.wordpress.com/2009/03/17/howto-change-the-materials-type-of-a-material-master/

    Regards

    Vinu

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 21, 2012 at 04:38 AM

    Dear Ameet,

    You can change material type through T.Code - MMAM but this will only possible when there is no transaction against the material is pending and no open document is assigned as said by Vinu.

    Please refer: http://help.sap.com/saphelp_470/helpdata/en/ff/515b2449d811d182b80000e829fbfe/content.htm

    Regards,

    Tarun

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.