Hi Gurus  -

We have some materials (Finished Goods) which were earlier assigned as Pricing Reference Material itself. Now we want to change to Semi Finished but its not allowing me to do so. Any idea what the issue can be ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Ameet ,

If there is any open documents assigned to the material, then you cannot change it. Make sure no open documents assigned to it.

Refer the below link.

http://sapmm.wordpress.com/2009/03/17/howto-change-the-materials-type-of-a-material-master/

Regards

Vinu

Answers (1)

Answers (1)

ripu123in
Explorer
0 Kudos

Dear Ameet,

You can change material type through T.Code - MMAM but this will only possible when there is no transaction against the material is pending and no open document is assigned as said by Vinu.

Please refer: http://help.sap.com/saphelp_470/helpdata/en/ff/515b2449d811d182b80000e829fbfe/content.htm

Regards,

Tarun