We have business scenario in material specification Example  we have 10 characteristics against material for those characteristics out of 10 i will maintain specification around 8 to 9 characteristics remaining  formula or calculated characteristics. i Know  how to calculate characteristics values through inspection plan  but i am not aware  material specification is it possible in QS61 if any abody aware kindly guide me.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member42743
Active Contributor
0 Kudos

For calculated characteristics you must use an inspection plan which can be used in conjunction with a material specification.

Also, depending on your processes and if you are batch managed using general characteristics, you can perform some simple calculations using variant config functionality at the batch level.

I..e. results of inspected characteristics get copied to the batch where other general characteristics are populaed with calculated data from them.  this is not a good solution if the calculated characteristic is required for approvng the material in QM.  But it does work well when you jsut need to do some type of conversion or simple calculation.