Hello,

I have a question regarding MAP after GR.

eg: Production order header material A $100, Production order component material B $150

Both is FERT materials.

Currently:

After GR, the MAP for mat A still remain as $100. The difference of $50 must be settled.

Desired:

After GR, the MAP for mat A will change to $125. No settlement.

Is this possible? I'm not sure where can I do this set up for the GR cost roll up as the material number use is different. Thanks.

Regards

Tif