Dear All,
My client is using Strategy 40 for all it's MRP type PD materials.
When I am creating production order, system automatically/by-default take scheduling type as "Backwards".
For this I have checked material master of the material but there is no Backward scheduling maintained.
My question is, When strategy is 40, does system takes automatically scheduling type as "Backwards"?
Thanks,
Naresh