Breakdown report

Former Member
0 Kudos

Hi,

Our requirement is how to capture the down time of the superior equipment,if notification is raised for the equipments assigned to superior.

We have one equipment which is combination of Motor and Pump.I have assigned these two to superior equipment,for example generator.

If I run notification on any of the sub equipment it effects the function of the superior too,so i want to adhere the same down time to superior,when ever i run notification on sub equipment and if I run notification on superior it should be captured at superior only not at sub equipment.

Even I have observed that in this case of superior and sub concept even cost capturing is not happening at superior level only restricted to individual level.

If I maintain superior as functional location I could see cost capturing at Functional location ,but breakdown time not been captured at Functional location,if i maintain down for individual equipments under same functional location.

Regards,

Sudhakar

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Cost will get accumulated to last equipment level (in this case, pump or motor). This will get accumulate to Functional Location level next but not at Superior equipment level. This is standard SAP.

So you have to use custom report to make the same hierarchy of cost with physical hierarchy.

---------------------------------------------------------------------------------------------------------------

And whenever you create Breakdown notification for sub equipment, as mentioned earlier, you can use equipment affected option to mention the superior equipment. As its not actual downtime of superior equipment, SAP (standard) will not capture that in analysis reports.

Here you have to go for some development again by creating one notification for the equipment affected whenever notification is created for sub equipment. Also the all the details should be updated whenever the details get updated for sub equipment.

former_member214626
Active Contributor
0 Kudos

Hi Mahesh ,

I think Same thing is provided with MCI3 .For example say you are having two FL :

1. AA - NN

2. AA - NN - 1

Now 1 notification/order is generated against AA-NN-1 with cost  Rs . 2000 . Other notification/order generated against AA-NN with Cost Rs 1000 .

As he wants to capture the accumulative cost at AA-NN (which should be 2000 + 1000 = 3000 ) then he can use MCI3 with searching crieteria :

FL = AA-NN* .

then system will show the cost FL wise but the total cost will also appear in first line .

For the equipment breakdown time (where he is taking superior as FL) , Iw29 can be used again .

REgards

Former Member
0 Kudos

I think, he is looking for cumulative cost at superior equipment & then at Functional location level.

Mr. Sudhakar,

Please confirm about your requirement.

Former Member
0 Kudos

Yes Mr.Maheswaran,I am looking at cumulative cost analysis and breakdown analysis at superior level.

Regards,

Sudhakar

Former Member
0 Kudos

Then you can't get it from standard reports, you should go for some development.

former_member214626
Active Contributor
0 Kudos

Hi Sudhakar ,

Accumulative cost at superior equipment in standard can be done with a workaround . For that your equipment number range should be external and with external number range you should create some hierarchy between sub equip. and superior equipment . In this case

For Cost you can use MCI3 and for breakdown hours you can use IW29 .

Otherwise as Mahesh said , go for a development .

Regards

Former Member
0 Kudos

In notification, activate screen system availability. In system availability you will be able to enter equipment affected. There you can capture breakdown for superior eq/fl.

former_member214626
Active Contributor
0 Kudos

Hi Yogesh ,

Even after activating that screen , only we can filter the results for list of notifications . But I think Sudhakar is looking for Cost and there is no field for eqp/FL effected in MCI3 .

Regards

former_member214626
Active Contributor
0 Kudos

Hi Sudhakar ,

While using reports like MCI3 , use post fix * with superior FL . For example say you are having two FL :

1. AA - NN

2. AA - NN - 1

Here AA- NN is superior . if in MCI3 , in searching screen you use AA- NN* then you will get the total cost at AA-NN and also at the individual FL .

Same method u can use for equipments .

Regards

Former Member
0 Kudos

Hi SAP PM,

I tried the above ,but it is not working out with FL and superior .

Regards,

Sudhakar

former_member214626
Active Contributor
0 Kudos

Hi Sudhakar ,

Can you please paste screenshot of results and also please share what searching crieteria you are using because it should work .

Regards