Unable to See Custom Field value in the Idoc at ECC

Hi all,

We  are using ZINVOIC02  custom idoc  where  we create a custom zsegment with addition of two field. 

We replicate the required changes in DEV and TEST both. 

Its file to Idoc  interface.    But when do the testing in DEV it works fine and  new field values apppeared at ECC side  in WE02.

We transport all the ABAP development and PI development  Object to TEST environment. 

But when tested in  TEST it does not show the  new field value in IDoc.

we increase the payload persistance at PI side  to show how the Idoc structure is creating and it shows well and populating new field in  the IDoc structure.

This is interface was working earlier  with other custom fields but this time it did not .

We retransport all the configuration  from  DEV to TEST and compare the same. 

1. We checked the version History , logs, caching in PI and its fine.

2.  Can we check somthing at  ECC side to ensure what its receiving from  PI side,

3.   Can we have related transaction for Idoc to validate , do we need to activate again  any thing in TEST still we are transporting those changes

Any input or  link on that would be thanks ful

let me know if any other input required to resolve this issue. 

regards

Ram Singhal

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Nov 16, 2012 at 07:45 PM

    Hi Ram,

    Are you able to see new segment in WE 02-Test environment? if yes then problem with meta data , follow Anupam suggestion,import meta data once again.

    Regards,

    Raj

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 16, 2012 at 07:39 PM

    Hi Ram,

                 In the ECC side check if the transport of changes (related to idoc structure) to TEST env is complete or not. Secondly whether structural changes have been released or not in ECC. Thirdly during transport please check if you have transferred the external definition related to the idoc(if any) or not. 4thly you need to check if in message mapping the new fields are showing properly or not. Finally use idx2 transaction in PI to delete the idoc metadata  and rerun the scenario.

    Regards

    Anupam

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanks  Anupam,

      We check all the transport both in PI and ECC ,

      Both side structure is available.

      We are on PI 7.3 java only stack , So no IDX2 requried.   Message mapping works fine.

      We increase the persistance level too  to see the inbound payload and it shows new field in the idoc after all the execution completed in  PI.

      regards

      Ram