SAP AFS MRP Run

Hi All,

We are working on SAP AFS, We are seeing some issues with Make to Stock. The strategy group we are using is 40.

We have a Production order ( Semi finished ) with quantity 100, We are having 3 operations, we are confirming the first operation with excess quantity say 150,

The Semi finished production order is in PCNF status (with first operation 0010 confirmed) with excess confirmation and is being counted by MRP as inventory. So when MRP runs for FG it looks at this PCNF semi finish order and accounts for these excess confirmations and proposes reduced quantities on semi finished orders for next requirements.

For example :

Semi finished Order 1 : Sched Qty 100, Operation 0010 confirmed 150 (50 excess – confirmation). Please note other operations are not confirmed yet so no final inventory exist.

FG Order 1 : Required quantity 100 consumes first 100 of the semi finish order.

FG Order 2 : Required quantity 60. MRP uses the 50 from first semi finished order and generates a planned order with quantity 10.

Is there a setting in the system, which can instruct MRP to only account for inventory which is confirmed and ignore over confirmations at operation level.

Thanks in Advance.

Vj

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Nov 19, 2012 at 09:46 AM

    Hi,

    In scope of check, keep the "Incl Production orders" field empty. Assign the specific checking group in the material master and the checking rule to MRP group which should be assigned to material in the MRP1 view. But if you use this setting the MRP will not consider the production order quantities completely.

    Try this and revert back if this your requirement.

    Regards,

    Krishna Chandra

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 19, 2012 at 10:43 AM

    Hi,

    IN SPRO: OPJJ for your checking rule uncheck the filed "Incl. production orders" and try.

    Do it for both 1 and 2.

    Regards,

    Alok Tiwari

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.