HOW TO ADD KEY FIGURE TO ACTIVATED PLANNING AREA

UNABLE TO ADD KEY FIGURE TO PLANNING AREA

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member187488
Active Contributor
0 Kudos

Hello,

If you're using an SCM system equal to to higher than SCM7.0, I guess that you're using the "change key figure settings" functionality in transaction /sapapo/msdp_admin.

If this is the case for you, you may get the attached error in a system which acts as a target system to which you transport the change. Please understand that this error is unavoidable during transport of key figure change. Though you do not get the error in source system.

In this case, you either do the same change directly in target system, or you must de-initialize the planning area in target system and re-initialize it again.

If you get this error in other scenarios, you'll have to do data backup -> de-initialize PA -> re-initialize PA -> data restore to eliminate the error. This error (COM error 40,134) cannot be corrected by the consistency check report.

Best Regards,

Ada

Former Member
0 Kudos

Hello Kalyan,

I guess you can directly go in change mode and  add/delete the  Key figures to PA.

Using /sapapo/msdp_admin

Regards,

Anurag

Former Member
0 Kudos

Hi Kalyan,

You want to add a new key figure into planning area or want to see the data for key figure in planning book/data view.

For adding a key figure in planning area:

You need to de initialize the plannig area and then you can add a key figure, make sure you take back up of time series data before deactivation. Once you add the key figure then initialze the the planning area agin.

To see the data in planning book/data view:

Yoo need to run Time series Consistency check program.

SAPAPO/TS_LCM_CONS_CHECK

Hope this helps!

Thanks