Dear Expert,
I have maintain one material (ROH) planned delivery time as 1 day in MRP 2 screen and when i run the MRP today(say 16.11.2012) for it's FERT then in case of forward scheduling system should give the Receipt date of ROH as 17.11.2012, but the system is giving the receipt date as 19.11.12. Kindly confirm why system is considering sat & sun as weekly off day for planned delivery time.
Note purchasing processing in plant paramater we have mentioned as zero. Please find below screen shots