Skip to Content
0
Nov 16, 2012 at 07:10 AM

Planned Order generation for Sub-assembly

282 Views

Dear Team,

I am working on make to stock scenario. In the material master of my FERT and HALB material i have provided the strategy as 10- make to stock production and i am planning with MRP Area.

When i run MRP in MD01, the planned orders are created for FERT and DepReq is getting created for HALB material. After converting the planned order to production order for my FERT item, i am expecting that the planned order will be generated for HALB item. But the system is not generating planned order for my HALB item, in-stead it generates order reservation for my HALB item. Is there any configuration to be set to modify this behavior or system will only generate order reservations for HALB items for dependent requirements?

Note: I am working in MRP Area based planning.

thanks