Dear Experts,
I have a finished product say ' A ' , that can be made from interchangeable raw material 'A1' , 'A2' , 'A3'.
The BOM of A is A1, A2, A3. with 1 qty each.
In alternate item group I am defining
A1 as AlternateGroup=A
Priority=1
Strategy=1
Usage Probability=60
A2 as AlternateGroup=A
Priority=1
Strategy=1
Usage Probability=30
A3 as AlternateGroup=A
Priority=1
Strategy=1
Usage Probability=10
I have a stock for ' A2 =100 '. and ' A3 = 10 '.
The demand for ' A ' is 1000.
Expected Result : When I run MRP I should get PR for ' A1 = 600 ' , ' A2 = 200 ' , ' A3 = 90 '.
but the system is not considering the stock of A2 and A3 it is giving the result as A1=600 , A2=300 , A3=100.
Please Help me to get the expected result.
Regards
Zonee.