Nov 16, 2012 at 06:15 AM

How may I configure the mentioned MRP scenario?

28 Views

Dear Experts,

May I ask if the follow MRP scenario available and how to be configured?

There are 2 Plants, Plant 1000 and 2000. Both plants contains materials which will be replenish by stock transfer from the other plant.

What I want to do is, for materials which will be replenish by stock transfer, they will execute MRP run on every Monday, and for materials replenish by external procurement will execute MRP run on every Friday.

Is the scenario available to be configured? If true, how?

Thanks,

Steven