Hi Guru's,
After system upgrade to EPH5 we facing the issue in work order actual cost value for Internal labor.
We are using BAPI 'BAPI_ALM_CONF_CREATE' to confirm the work order after the confirmation when we check the order in IW 32/33 tcode>> costs tab>>overview >>nternal labor's actual costs it showing as '0' although it has a value . If we click on 'report Plan /actual' on the same screen it shows correct atcual cost value. Please guide me.